CONTRACT AWARD NOTICE - UTILITIES
|
Section I: Contracting Entity
|
I.1)
|
Name, Address and Contact Point(s)
|
|
Moyle Interconnector Limited |
1st Floor, The Arena Building, 85 Ormeau Road |
Belfast |
BT7 1SH |
UK |
Paddy Larkin |
+44 2890437580 |
paddy.larkin@mutual-energy.com |
|
http://www.mutual-energy.com
|
|
I.2)
|
Main activity or activities of the contracting entity
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
Section II: Object of the Contract
|
II.1)
|
Description
|
II.1.1)
|
Title attributed to the contract by the contracting entity
Supply and repair of Moyle Interconnector cables.
|
II.1.2(a))
|
Type of works contract
|
II.1.2(b))
|
Type of supplies contract
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
|
II.1.2(c))
|
Type of service contract
|
II.1.2)
|
Site or location of works, place of delivery or performance
|
II.1.3)
|
This notice involves
 |
II.1.4)
|
Short description of the contract or purchase(s)
Moyle Interconnector Limited (Moyle) has awarded a contract for the design, manufacture, testing, supply, installation, jointing and commissioning of replacement subsea metallic return conductors.
|
II.1.5)
|
Common Procurement Vocabulary (CPV)
|
|
|
|
31321220 |
|
|
|
|
|
II.I.6)
|
Contract covered by the government procurement agreement (GPA) No |
II.2)
|
Total final value of the contract(s) awarded
|
II.2.1)
|
Total final value of the contract(s) awarded
|
Section IV: Procedure
|
IV.1)
|
Type of procedure
|
IV.1.1)
|
Type of procedure |
IV.2)
|
Award criteria
|
IV.2.1)
|
Award criteria
 |
IV.2.2)
|
An electronic auction has been used No |
IV.3)
|
Administrative information
|
IV.3.1)
|
Reference number attributed to the notice by the contracting entity |
IV.3.2)
|
Previous publication(s) concerning the same contract
Other previous publications
|
Section V: Award of contract
|
V.1)
|
Award and Contract Value
|
|
|
|
|
V.1.1)
|
Date of contract award |
V.1.2)
|
Numbers of offers received |
V.1.3)
|
Name and address of economic operator to whom the contract has been awarded
Nexans Norway A.S. |
Innspurten 9 |
Oslo |
0663 |
NO |
|
|
|
|
|
V.1.4)
|
Information on value of contract
|
V.1.5)
|
The contract likely to be subcontracted No
|
|
Short description of the value/proportion of the contract to be subcontracted |
V.1.6)
|
Price paid for bargain purchases
|
Section VI: Complementary Information
|
VI.1)
|
Contract related to a project and/or programme financed by community funds? No
|
VI.2)
|
Additional Information
|
VI.3)
|
Procedures for appeal
|
VI.3.1)
|
Body responsible for appeal procedures
High Court of Justice, Northern Ireland |
Chichester Street |
Belfast |
BT1 3JF |
UK |
adminoffice@courtsni.gov.uk |
+44 2890235111 |
|
|
|
|
Body responsible for mediation procedures
|
|
|
|
|
|
|
|
|
|
VI.3.2)
|
Lodging of appeals
In accordance with Utilities Contracts Regulations 2006 (as amended).
|
VI.3.3)
|
Service from which information about the lodging of appeals may be obtained
|
|
|
|
|
|
|
|
|
|
VI.4)
|
Dispatch date of this Notice 13-02-2015 |
ANNEX D
Justification for the choice of the negotiated procedure without prior call for competition
|
|
|


 |
|
 |
|



|
|
 |
|
 |
|
 |
|
 |
|
 |
|

 |
|
 |
|
|
 |
|
 |
|
Moyle required to place a contract for the replacement and repair of the existing Moyle Interconnector cables, which currently are only capable of operating at half capacity. The Moyle Interconnector is a 500MW HVDC interconnector between Scotland and Northern Ireland. It is built as a dual monopole. The unique cables between the Scotland and Northern Ireland converter stations were supplied and installed by Nexans and commissioned by them in 2001. The two cables each consist of a high voltage core with a concentric metallic return conductor known as an integrated return conductor. Nexans is the only cable supplier in the world with operational experience of integrated return conductor cables and appropriately qualified cables and accessories. Moyle Interconnector Limited has appointed Nexans to replace the subsea integrated return conductors and supply spare lengths of the existing cables, without a formal competitive process for 2 reasons: 1. From a technical perspective only Nexans are able to deliver the project due to the need to connect into the existing power cable at the beach. Only Nexans have appropriately qualified personnel, methods, parts and equipment to make such connections and to make such spare cable. As the original supplier and installer of the cables, only Nexans have the expertise and understanding of the current cable to supply replacement cables in a manner which attracts an acceptable level of risk. 2. An opportunity has arisen which will mean that Moyle can take advantage of a particularly advantageous bargain (as described in Regulation 17(1)(j) of the Utilities Contracts Regulations 2006) and that bargain: — is considered a particularly advantageous opportunity; — is only available for a very short period of time; and — incorporates a price which is considerably lower than market prices.
|
|