The procurement documents are available for unrestricted and full direct access, free of charge at:
Lot No: 1
II.2.1) Title
Lot 1 --Bricks, Sand & Cement, Plaster & Plasterboard and Small Aggregates
II.2.2) Additional CPV code(s)
44111000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 1 - Bricks, Sand & Cement, Plaster & Plasterboard and Small Aggregates
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.6) Estimated value
Value excluding VAT:
2 200 000.00
GBP
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 2
II.2.1) Title
Lot 2 - Floor and Wall Tiles
II.2.2) Additional CPV code(s)
44111000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 2 - Floor and Wall Tiles
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 3
II.2.1) Title
Lot 3 - UPVC Trim
II.2.2) Additional CPV code(s)
44111000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 3 - UPVC Trim
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 4
II.2.1) Title
Lot 4 - Tools
II.2.2) Additional CPV code(s)
44500000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 4 - Tools
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 5
II.2.1) Title
Lot 5 - Hardware
II.2.2) Additional CPV code(s)
44500000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 5 - Hardware
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 6
II.2.1) Title
Lot 6 - Gas Bottles
II.2.2) Additional CPV code(s)
44612100
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 6 - Gas Bottles
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 7
II.2.1) Title
Lot 7 - Sundries and Miscellaneous
II.2.2) Additional CPV code(s)
44100000
44110000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 7 - Sundries and Miscellaneous
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 8
II.2.1) Title
Lot 8 - Roofing Materials
II.2.2) Additional CPV code(s)
44110000
44112000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 8 - Roofing Materials
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
Lot No: 9
II.2.1) Title
Lot 9 - Sealants & Adhesives
II.2.2) Additional CPV code(s)
44100000
II.2.3) Place of performance
NUTS code:
UKC22
II.2.4) Description of the procurement
This Framework Contract will ensure availability of suitable Suppliers for the supply of goods required as detailed in the Specification included within the Tender Documents.
It is anticipated the Contract will commence on 1st September 2024 and is for an initial 24 month period with the option to extend for up to a further two, twelve month periods. A mini competition will be carried out annually between the successful Contractors which may result in re-ranking. The Successfully awarded
Contractors will be required to work together with North Tyneside Council (the Authority) to drive improvements and support the aims and ambitions of the Contract.
The Framework consists of the following 8 lots and a maximum of 3 Contractors will be on each Lot, there is no limit to the number of Lots you can bid for, where you are unable to provide a price for a product, the Authority will apply the highest price submitted from all bids and you must price at least 80% of each Lot being applied for Contract 15 Building Supplies.
Lot 9 - Sealants & Adhesives
II.2.5) Award criteria
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7) Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 48
This contract is subject to renewal: Yes
Description of renewals:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.9) Information about the limits on the number of candidates to be invited
II.2.10) Information about variants
Variants will be accepted:
No
II.2.11) Information about options
Options:
Yes
Description of options:
Award Criteria
The full detail's of the award criteria are included in the Tender Documents
Contract Duration
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority and in line with the Authority Requirements for the Framework.
Number of Successful Tenderers
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot
Tenders can be accessed by the following link =
https://procontract.due-north.com
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
No
The initial contract is for 24 months with two options to extend for up to a further 12 months each after which renewals will be undertaken in accordance with the Authority's contract Standing Orders and at the sole discretion of the Authority.
The maximum number of Contractors to be awarded on the Framework = 3 (three) per Lot