Description of the goods or services required
Scopes:
Civils construction elements included in the framework:
- Level Boarding
- Under Track Crossings
- Installation of Station Tactiles
- Earthworks schemes
- Retaining wall schemes
- Culvert construction
- Track drainage
Cwmbach Station Level Boarding
Drawings - Cwmbach Station
Supplier to carry out their own takeoff to confirm actual works and quantities
- Corus Style Section - contains but not limited to
- Remove front steel angle
- Remove Coper and Tactile
- Clean off steel deck
- Make steel work adjustments
- Reinstall coper to new line and level
- Install tactile
- Adjust platform surface to suit
- Reapply white/yellow lines
- Supply spare materials (10%)
- Block & Beam - contains but not limited to
- Remove Cope and Tactile
- Clean off surface
- Reinstall coper to new line and level
- Install tactile
- Adjust platform surface to suit
- Reapply white/yellow lines
- Supply spare materials (10%)
- Engineer provision
- Setting out and gauge surveys
- As-built production of level boarding
- Quality control - BIM360 checklists and sign off
Working/access availability
- Works to be planned to be carried out Midweek Nights based on 7hour possession times and a Saturday night Possession window of 8 hours
Additional Information
- Schedule of rates (produce list of competencies)
- Mid week days
- Mid week nights
- Weekend days
- Weekend nights
- Bank Holidays
- Welfare Van
- Groundhog
- List of all materials including rates
- Cancellation notice period
- Stand Down Rates
Attendances
- BB/AIW to supply Main Welfare Accommodation
- BB/AIW will provide Possession Management Staff
- BB to provide access to digital systems - supplier to provide hardware (iPAD)
- Supplier to provide all site labour including COSS/SWL
- Supplier to ensure that COSS/SWL are to have iPADs to use the digital epics system
- Supplier to provide localised welfare as required
- Supplier to provide all materials (inc water etc)
- Supplier to provide all plant and tools (inc site lighting)
Pentrebach Station Level boarding
Drawing - Pentrebach LB
Supplier to carry out their own take off to confirm actual works and quantities
- Supplier to provide full details of Method and Risks
- Standard platform construction - contains but not limited to
- Remove Coper and Tactile
- Clean off surface
- Raise blockwork and over sail blocks
- Install FP McMann Tactile and coper unit
- Raise ironwork
- Install edging kerbs to back of platform and around cabinets
- Alter platform drainage
- Install surfacing to suit new coper levels and falls as per design
- Reapply white/yellow lines
- Supply spare materials (10%)
- Engineer provision
- Setting out and gauge surveys
- As-built production of level boarding
- Quality control - BIM360 checklists and sign off
Working/access availability
- Works to be planned to be carried out during a blockade, please can the supplier identify how long they require to complete these works.
Additional Information
- Schedule of rates (produce list of competencies)
- Mid week days
- Mid week nights
- Weekend days
- Weekend nights
- Bank Holidays
- Welfare Van
- Groundhog
- List of all materials including rates
- Cancellation notice period
- Stand Down Rates
Attendances
- BB/AIW to supply Main Welfare Accommodation
- BB/AIW will provide Possession Management Staff
- Supplier to provide all site labour including COSS/SWL
- Supplier to ensure that COSS/SWL are to have digital tablets to use the digital epics system
- Supplier to provide localised welfare as required
- Supplier to provide all materials (inc water etc)
- Supplier to provide all plant and tools (inc site lighting)
Taffs Well UTX
Taffs Well UTX Drawing - TRAN01-KAW-R0-R2P-DDR-C-CV-000114 - 26082020.pdf
Standard UTX Construction
- Procurement of UTX Materials
- Installation of Up Main Chamber
- Installation of 9.150m 4 way duct crossing
- Installation of Down Main Chamber
- Installation of hardstanding's and handrail
- Handback Engineer following each shift in the Track Support Zone
- All plant and materials to complete the works (excluding RRV's)
- Track monitoring shift following construction
- 7 Days following construction in the first week
- 2 days in the second week
- 2 days in the third week
- 1 day in the fourth week
- Temporary works supervisor provision
- Engineer provision
- Setting out of snake grid coordinates
- As-built production of UTX
- Quality control - BIM360 checklists and sign off
Additional Information
- Schedule of rates (produce list of competencies)
- Mid week days
- Mid week nights
- Weekend days
- Weekend nights
- Bank Holidays
- Welfare Van
- Groundhog
- List of all materials including rates
- Cancellation notice period
- Stand Down Rates
Attendances
- RRV's will be provided by BB
- Temporary works provided by BB
- BB/AIW to supply Main Welfare Accommodation
- BB/AIW will provide Possession Management Staff
- Supplier to provide all site labour including COSS/SWL
- Supplier to ensure that COSS/SWL are to have digital tablets to use the digital epics system
- Supplier to provide localised welfare as required
- Supplier to provide all materials (inc water etc)
- Supplier to provide all plant and tools (inc site lighting)
NOTE: To register your interest in this notice and obtain any additional information please visit the Sell2Wales Web Site at https://www.sell2wales.gov.wales/Search/Search_Switch.aspx?ID=120841.
|