Contract Notice

Llangollen 2020 - Highways & Environmental Improvements & A5 Traffic Signals, Hill/Hall Street Junct

  • First published: 12 July 2021
  • Last modified: 12 July 2021
  • This file may not be fully accessible.

  •  

You are viewing an expired notice.

Contents

Summary

OCID:
ocds-kuma6s-112301
Published by:
Denbighshire County Council
Authority ID:
AA0280
Publication date:
12 July 2021
Deadline date:
06 August 2021
Notice type:
Contract Notice
Has documents:
No
Has SPD:
No
Has Carbon Reduction Plan:
N/A

Abstract

Works will consist of the following main items :- > General site clearance including the removal and re-siting of existing pedestrian signals and associated equipment, lighting columns and street furniture; Façade & Structural Surveys of all buildings adjacent to works areas ; > Contractor provision of a dedicated Site Liaison Officer ; > Temporary traffic management including pedestrian and traffic lights ; > Excavation of existing kerbs and footway construction on Castle Street, Market Street, Bridge Street and the A539/A542 junction ; > Installation of new pc kerbs and footway construction using natural stone materials on Market Street ; > Construction of new kerb alignment and widened footways using natural stone materials on A539/A542 junction, Castle Street and Bridge Street ; > Replacement of existing chamber covers with recessed precinct covers for paving ; > Contractor design and implementation of basement / cellar lights in footways ; > Planing and resurfacing of the existing carriageways on Castle Street and A539/A542 junction ; > Installation of thermal expansion joints over bridge ; > Installation of raised tables on 2 junctions along Castle Street ; > Installation of new uncontrolled crossing points ; > Widening and ramping of the existing controlled crossing on A539/Mill Street ; > New carriageway drainage ; > Street Lighting Columns and lanterns on the Dee Bridge. New lanterns and bracket arms only on remainder of Castle Street ; > Road Markings and anti-skid ; > Road and destination signage ; > Street furniture eg. bins, guardrail, tree & tree maintenance. I addition to the above, DCC have been requested by NMWTRA to incorporate into the works 2 additional project areas for construction. The design for these have been carried out by YGC and Siemens. The works consist of the following main items :- > Replacement of the existing traffic signals and all associated equipment on the A5/Castle Street Junction and linking of the signals via MOVA to the 2 existing controlled crossings on the east and west sides of the A5 ; > Remodelling of the Hill / Hall Street Junction off the A5 outside the Armoury Building.

Full notice text

CONTRACT NOTICE – NATIONAL

WORKS

1 Authority Details

1.1

Authority Name and Address


Denbighshire County Council

Wynnstay Road,

Ruthin

LL15 1YN

UK

Jayne Valentine

+44 1824712612

jayne.valentine@denbighshire.gov.uk

www.denbighshire.gov.uk
https://supplierlive.proactisp2p.com/
https://supplierlive.proactisp2p.com/

1.2

Address from which documentation may be obtained


Denbighshire County Council

Wynnstay Road,

Ruthin

LL15 1YN

UK


+44 1824712612

jayne.valentine@denbighshire.gov.uk

www.denbighshire.gov.uk

1.3

Completed documents must be returned to:


Denbighshire County Council

Wynnstay Road,

Ruthin

LL15 1YN

UK


+44 1824712612

jayne.valentine@denbighshire.gov.uk

www.denbighshire.gov.uk

2 Contract Details

2.1

Title

Llangollen 2020 - Highways & Environmental Improvements & A5 Traffic Signals, Hill/Hall Street Junct

2.2

Description of the goods or services required

Works will consist of the following main items :-

> General site clearance including the removal and re-siting of existing pedestrian signals and associated equipment, lighting columns and street furniture;

Façade & Structural Surveys of all buildings adjacent to works areas ;

> Contractor provision of a dedicated Site Liaison Officer ;

> Temporary traffic management including pedestrian and traffic lights ;

> Excavation of existing kerbs and footway construction on Castle Street, Market Street, Bridge Street and the A539/A542 junction ;

> Installation of new pc kerbs and footway construction using natural stone materials on Market Street ;

> Construction of new kerb alignment and widened footways using natural stone materials on A539/A542 junction, Castle Street and Bridge Street ;

> Replacement of existing chamber covers with recessed precinct covers for paving ;

> Contractor design and implementation of basement / cellar lights in footways ;

> Planing and resurfacing of the existing carriageways on Castle Street and A539/A542 junction ;

> Installation of thermal expansion joints over bridge ;

> Installation of raised tables on 2 junctions along Castle Street ;

> Installation of new uncontrolled crossing points ;

> Widening and ramping of the existing controlled crossing on A539/Mill Street ;

> New carriageway drainage ;

> Street Lighting Columns and lanterns on the Dee Bridge. New lanterns and bracket arms only on remainder of Castle Street ;

> Road Markings and anti-skid ;

> Road and destination signage ;

> Street furniture eg. bins, guardrail, tree & tree maintenance.

I addition to the above, DCC have been requested by NMWTRA to incorporate into the works 2 additional project areas for construction. The design for these have been carried out by YGC and Siemens. The works consist of the following main items :-

> Replacement of the existing traffic signals and all associated equipment on the A5/Castle Street Junction and linking of the signals via MOVA to the 2 existing controlled crossings on the east

and west sides of the A5 ;

> Remodelling of the Hill / Hall Street Junction off the A5 outside the Armoury Building.

NOTE: To register your interest in this notice and obtain any additional information please visit the Sell2Wales Web Site at https://www.sell2wales.gov.wales/Search/Search_Switch.aspx?ID=112301.

2.3

Notice Coding and Classification

45200000 Works for complete or part construction and civil engineering work
1013 Conwy and Denbighshire

2.4

Total quantity or scope of tender

3 Conditions for Participation

3.1

Minimum standards and qualification required

Works will consist of the following main items :-

> General site clearance including the removal and re-siting of existing pedestrian signals and associated equipment, lighting columns and street furniture;

Façade & Structural Surveys of all buildings adjacent to works areas ;

> Contractor provision of a dedicated Site Liaison Officer ;

> Temporary traffic management including pedestrian and traffic lights ;

> Excavation of existing kerbs and footway construction on Castle Street, Market Street, Bridge Street and the A539/A542 junction ;

> Installation of new pc kerbs and footway construction using natural stone materials on Market Street ;

> Construction of new kerb alignment and widened footways using natural stone materials on A539/A542 junction, Castle Street and Bridge Street ;

> Replacement of existing chamber covers with recessed precinct covers for paving ;

> Contractor design and implementation of basement / cellar lights in footways ;

> Planing and resurfacing of the existing carriageways on Castle Street and A539/A542 junction ;

> Installation of thermal expansion joints over bridge ;

> Installation of raised tables on 2 junctions along Castle Street ;

> Installation of new uncontrolled crossing points ;

> Widening and ramping of the existing controlled crossing on A539/Mill Street ;

> New carriageway drainage ;

> Street Lighting Columns and lanterns on the Dee Bridge. New lanterns and bracket arms only on remainder of Castle Street ;

> Road Markings and anti-skid ;

> Road and destination signage ;

> Street furniture eg. bins, guardrail, tree & tree maintenance.

I addition to the above, DCC have been requested by NMWTRA to incorporate into the works 2 additional project areas for construction. The design for these have been carried out by YGC and Siemens. The works consist of the following main items :-

> Replacement of the existing traffic signals and all associated equipment on the A5/Castle Street Junction and linking of the signals via MOVA to the 2 existing controlled crossings on the east

and west sides of the A5 ;

> Remodelling of the Hill / Hall Street Junction off the A5 outside the Armoury Building.

4 Administrative Information

4.1

Type of Procedure

Single stage

4.2

Reference number attributed to the notice by the contracting authority

WKS1000479REQ

4.3

Time Limits

Time-limit for receipt of completed tenders
    06-08-2021  Time  15:00

Estimated award date
 13-08-2021

4.5

Language or languages in which tenders or requests to participate can be drawn up

EN  CY 

4.6

Tender Submission Postbox

5 Other Information

5.1

Additional Information

(WA Ref:112301)

Under the terms of this contract the successful supplier(s) will be required to deliver Community Benefits in support of the authority’s economic and social objectives. Accordingly, contract performance conditions may relate in particular to social and environmental considerations. The Community Benefits included in this contract are:

Examples of Community Benefits to be provided for Llangollen 2020 – Highway & Environmental Improvements :-

1. Commitment to make sub‐contracting, and supply opportunities visible to local SMEs

2. Targeted training and employment :

3. Support local communities by introducing Active travel or environmental benefits in Llangollen

4. Sponsorship support - Sponsorship of local sports team

5. Reduction in CO² emissions and energy use during the construction

6. Site Waste Management Plan

7.Improved efficiency and management of transport miles of people and products

8. Family Active Travel training

The buyer considers that this contract is suitable for consortia bidding.

5.2

Additional Documentation

5.3

Publication date of this notice

 12-07-2021

Coding

Commodity categories

ID Title Parent category
45200000 Works for complete or part construction and civil engineering work Construction work

Delivery locations

ID Description
1013 Conwy and Denbighshire

Alert region restrictions

The buyer has restricted the alert for this notice to suppliers based in the following regions.

ID Description
There are no alert restrictions for this notice.

Document family

Notice details
Publication date:
12 July 2021
Deadline date:
06 August 2021 00:00
Notice type:
Contract Notice
Authority name:
Denbighshire County Council
Publication date:
05 February 2025
Notice type:
Contract Award Notice
Authority name:
Denbighshire County Council

About the buyer

Main contact:
jayne.valentine@denbighshire.gov.uk
Admin contact:
jayne.valentine@denbighshire.gov.uk
Technical contact:
N/a
Other contact:
jayne.valentine@denbighshire.gov.uk

Further information

Date Details
No further information has been uploaded.

0800 222 9004

Lines are open 8:30am to 5pm Monday to Friday.

Rydym yn croesawu galwadau'n Gymraeg.

We welcome calls in Welsh.